# Safety About 175 V sits between the +65 V and −112 V rails. Treat every HV node as live until you have measured it. ## Design measures 1. **Only certified mains equipment.** The 12 V brick is the only mains-connected part. Buy a certified brand (e.g. Mean Well GST36A12) from a normal retailer, not AliExpress. 2. **Hardware HV watchdog.** The relay on the HV modules' 12 V feed is driven through a charge pump: ``` GPIO21 ──┤├──── A ──►|── B ───┬───────┬──── 2N7000 gate 2N7000 drain ─► relay IN (active-low) 100nF │ 1N4148 │ │ 2N7000 source ─► GND ┴ 1N4148 ═ 10µF ▯ 100k ▲ (anode GND) │ │ GND GND GND ``` Node A gets a diode to GND (cathode at A), and a diode from A to B (anode at A). This rectifies the toggling signal into a DC voltage on B. A constant high or low level gives no charge. The firmware toggles GPIO21 once per scanned row (about 2 kHz). If it crashes, or the pin sticks high or low, or the ESP32 resets, the cap discharges and the relay drops within about 1 s. A stuck row can't burn the panel. (Check the polarity of your relay module's input. Some are active-low.) 3. **Fail-safe defaults.** The relay is normally open. Put a 10 kΩ pull-down on the watchdog path. Pull the panel ENABLE line to its *off* state at the 74HCT245 input, so a booting ESP32 can't light anything. 4. **Sequencing.** 5 V comes up, then the ESP32 boots and starts scanning, and only then does the watchdog close the relay. 5. **Fusing.** | Where | Fuse | |---|---| | 12 V input | 3 A | | Each HV module input | 1 A slow-blow | | Each raw HV rail | 100 mA fast | 6. **Discharge.** 330 kΩ bleeders on raw and regulated rails. HV-present LEDs are a hint only; always measure before you touch anything. 7. **Layout.** - Put all HV parts on one side, with ≥ 3 mm clearance between HV tracks. - Use wire and caps rated for ≥ 300 V/500 V. - Use a keyed connector to the panel. - Close it in a plastic enclosure with no exposed HV. - Tie all grounds at one point. 8. **Semiconductors from real distributors** (Mouser, Farnell, Reichelt). Fake HV transistors are common on AliExpress. ## Bring-up procedure 1. Build the 5 V and 12 V side only. Check the voltages. 2. Connect one HV module at a time, with **no load**. Set NCH6100HV #1 to 90 V and #2 to 130 V. Lock the pots with nail varnish. 3. Connect the regulator section, still without the panel. Check for about +65 V, −112 V and −100 V and that the bleeders discharge them. 4. Test the watchdog: stop toggling GPIO21, and the HV must drop within about 1 s. 5. Map the panel's power connector against the measured rails. Get a second check (photo/label). 6. First power-up with the panel: 1 kΩ in series with each HV rail and a running test pattern. Measure the current per rail, then remove the series resistors.